Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Background: On October 28th, emails were sent out informing customers that EverBright prices would be changing November 2nd. Account Managers were informed of the specific pricing changes for their organizations.

...

  • If customers reach out to support and have questions regarding pricing changes, they should reach out to their org admin (if the request came from a non-org admin) or their Account Manager (if request came from an org admin) for specifics.

  • If a customer expresses dissatisfaction about the updated pricing, send the following slack to #everbright-sales and tag the account manager:

FYI only - [customer name] with [organization] expressed dissatisfaction over price increase [enter their quote here]. Ticket is addressed but wanted you to be aware.

Before M1 approval

Note

Even though extensions will not be granted in M1, support will still forward requests to Deal Processing for final approval/denial

...

Info

The RIC assignment form is now part of the initial contract signing. Therefore, when a no cost change order (NCCO) is signed by the homeowner, the installer will need to complete a new RIC assignment form as a subtask.

  1. Navigate to Operations phase, go to the current milestone (M1 or M2) and
    click on the “NCCO” task. Then click the Generate button on the right side.

    Image Modified
  2. The “Generate Re-sign Contract” modal will open. Click on the Generate button to send the revised
    contract to your customers for their signatures

...

  1. Image Added

Requoting a job (post M1)

If a change order is needed for the amount financed, follow these steps:

  1. Navigate to the Quote phase

  2. Click on the “stacked 3 dot” icon next to the
    signed quote and select “Re-Quote” to regenerate the quote.

    Image Modified
  3. You will see options to re-quote with the original pricing (“use expired pricing”) or new
    pricing (“use current pricing”).

    Image Modified
  4. Select “Use expired pricing” and create the new quote

  5. Go to the Operations phase and the M2 workflow, select the new quote that was
    generated to use in the change order. Note: Because this quote has expired, it cannot
    be used in a new contract.