Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Table of Contents:

...

If the credit has expired, DP will not approve an M1 extension. The installer needs to cancel the workflow, requote, rerun credit, generate a new contract, and complete all milestone tasks:

'Hello,

The credit qualification is expired; therefore we are unable to grant a milestone extension for M1. In order to proceed, you will need to re-run credit, create a new quote and contract, complete all milestone tasks per the new workflow inclusive of the welcome call.

Regards,'

Info

If the previous contract was generated using expired pricing, the installer will have to requote with updated pricing. EB will not honor expired pricing for pre M1 cancellations

...

  • M3 extension requests will be considered by deal processing, however they must be within 90 days of the original milestone deadline. Navigate to M3 in Operations and click on the milestone feed tab to determine the original milestone deadline:

  • If within the 90-day window, the request can be completed by using the ‘direct milestone extension request’ in the platform or if the button is unavailable follow the ‘If the Milestone Extension Request button is not available’ instructions (see below for instructions)

...

Milestone

...

Extension Requests

Direct Milestone Extension Request

...

  • Navigate to the operations phase and click on the Milestone that needs to be extended. Click on the Request Milestone Extension toggle:

  • A window will pop up that will allow the installer to compose an email to deal processing to request a milestone extension. The installer also has the option to add additional recipients if they would like to have a copy sent to another party:

For incoming requests for Milestone Extensions

...

If the installer reaches out to Support to request an extension, we can process the request for them. However, they should be directed to use the Milestone Extension Request button in the futureto submit their request.

  • Navigate to the milestone needing an extension

    • confirm the extension request toggle is available

    • If in M2 -

    follow instructions above to see if a previous extension was granted
  • Click on the direct milestone extension request button (instructions above)

    • Add a custom note: ‘Support requesting extension on behalf of the installer’

  • When the request window pops up, click ‘Send’

    • No extensions will be granted

Back in the ticket, ‘reply to customer’ with the following canned response with screenshot included:

Hello,

Thank you for contacting EverBright support. We are pleased to inform that milestone extensions can be requested in the Operations phase of the platform. Please follow the instructions below to submit your request:

  1. Navigate to the Operations phase of your workflow

  2. Select the milestone needing an extension

  3. Click on the ‘Request Milestone Extension’ task

  4. A window will pop up allowing you to add others to the request and/or leave a custom note for deal processing

  5. Click ‘Send’

That’s it! An extension request will automatically be sent to deal processing for review. No further action is required on your part. Please allow 1-2 business days to complete the review. The result will be posted in the milestone feed section of the platform (see screenshot below for details). We are closing this ticket. Feel free to reach out if you need additional assistance.

Regards,

  • Once the milestone extension request has been sent to DP, the ticket can be closed.

    1. Resolution type - account management

If the Milestone Extension Request button is not available

...

(M1 or M3 only)

No M2 extensions will be granted. Otherwise, add dealprocessing to the request participants field before replying:

Deal Processing team:

[Organization], copied on this email, is seeking an extension for [customer name and address] for milestone [x]. Please let us know if this is approved or if you need additional information.

Thanks,

Other than the initial request above, any follow-up communication with DP should be done using internal notes. If DP has not responded within 24 hours, navigate to the operations phase of the workflow and check to see if the extension was granted. If not, send a slack message to DP to follow up

...