Background: Support might receive interactions coming from Installers asking for the removal of Liens placed by EverBright to the Installers
These liens were originally placed on the RIC’s due to the absence of an “Authoritative Copy” in DocuSign before the first financing in 2023
Process:
When an Installer contacts us requesting the removal of a Lien or questioning why it was placed follow these steps:
Step | Action | |
---|---|---|
1 |
| Kindly request the Installer to send a copy of the Lien in question
|
2 |
| |
3 |
| Primary Reason:
Secondary Reason:
Case Description:
|
NOTE: If you do not receive the requested Lien Copy within 2 Business days, Close the Case and note that no response was received | ||
4 |
| Also Upload the Lien Copy to the “Files” section in the case for proper documentation |
5 |
| |
6 |
|